Identification of Risk Factors for Delayed Time Schedule in Summarecon Serpong Playfield Preschool Project

Setiawan, Deni and Abigail, Stefanny (2022) Identification of Risk Factors for Delayed Time Schedule in Summarecon Serpong Playfield Preschool Project. In: Proceedings of the 1st International Conference on Emerging Issues in Technology, Engineering and Science ICE-TES, 2021, Bandung, Indonesia.

[thumbnail of Identification of Risk Factors for Delayed Time Schedule in Summarecon Serpong Playfield Preschool Project.pdf]
Preview
Text
Identification of Risk Factors for Delayed Time Schedule in Summarecon Serpong Playfield Preschool Project.pdf - Published Version

Download (423kB) | Preview

Abstract

Construction tasks are generally carried out beneath surroundings characterised with the aid of using various diploma of hazard and uncertainties, which could end result from ‘acknowledged’, ‘acknowledged- unknown’, and ‘unknown-unknown’ situations (Smith, 1999). Delays withinside the mission that may be as a result of numerous elements, each inner and outside elements. However, it can't be denied that during Indonesia stage of mission put off is pretty excessive and may be as a result of numerous elements, each inner and outside elements. The motive of this take a look at is to investigate the elements of put off withinside the implementation of the Playfield Preschool Summarecon Serpong mission. Final effects of the take a look at there are variations of opinion concerning the elements inflicting mission delays among mission people and teachers who're specialists withinside the area of production control. Based at the descriptive take a look at effects of the 6 classes of put off, it changed into discovered that the thing inflicting the best put off changed into the monetary class. More certain studies is wanted which may be analyzed greater deeply into the elements inflicting mission delays aside from the monetary class.

Item Type: Conference or Workshop Item (Paper)
Uncontrolled Keywords: Delay, Risk Factors, Risk Identification, Project, Construction
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD61 Risk Management
T Technology > TH Building construction
Depositing User: Martha Yovina
Date Deposited: 16 Sep 2026 07:56
Last Modified: 16 Sep 2026 07:56
URI: https://repo.maranatha.edu/id/eprint/533

Actions (login required)

View Item
View Item