Setiawan, Deni and Milyardi, Roi and Tan, Lie Ing and Rizkiana, C (2021) Risk Allocation Model for Cisumdawu Toll Road Projects. In: IOP Conference Series: Materials Science and Engineering, 28 November 2020, Jakarta, Indonesia.
Risk Allocation Model for Cisumdawu Toll Road Projects.pdf - Published Version
Download (573kB) | Preview
Abstract
In the Cisumdawu Toll Road project there are some complex problems, including the first tunnel structure in Indonesia that functions as a toll road. This complex construction project is currently experiencing delays which creates risks for project delays. In this study the aim is to identify risks and create an optimal risk allocation model between the project owner and the contractor. The allocation of risk between project owner and contractor in a contract plays an important role for the success of the project. It should be based on a proper assessment of the involved risks and choosing the party best able to manage them. This research was obtained about risks that can be impacted by the project in each phase. The scope of non- excusable factors often is considered a contractor's fault which results in project construction. Based on the results of descriptive test of the 5 main risks include the most important risk in the Cisumdawu Toll Road Construction Phase II (STA 9+750 – STA 27+100) is soil work. The results show that the soil work risk should bear by the contractors by lump sum fixed price contract
| Item Type: | Conference or Workshop Item (Paper) |
|---|---|
| Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD61 Risk Management T Technology > TE Highway engineering. Roads and pavements |
| Depositing User: | Martha Yovina |
| Date Deposited: | 14 Sep 2026 03:17 |
| Last Modified: | 14 Sep 2026 03:17 |
| URI: | https://repo.maranatha.edu/id/eprint/520 |